Monday, November 17, 2008
Saturday, October 25, 2008
Roof and Third Floor Added
Thursday, October 9, 2008
Second Floor Framing
The framers spent a few days getting the second floor fraing into place. The roof deck and third floor garden rooms will hopefully be done next week. The following photo is the house looking North from across 23rd street.

This is the rear of the house looking South from the back yard.

This is the rear of the house looking South from the back yard.
This is the view looking out the Second Floor, South-West bedroom. You can see Lion's gate Bridge.
This is the view looking out the Second Floor, North-West bedroom. When it isn't cloudy you can see more of the North Shore mountains.
Tuesday, September 30, 2008
Up it Goes!
Framing of the first floor exterior and interior walls started yesterday. Other than some minor issues with window heights, it is going pretty well. Second floor joists and decking will begin tomorrow. The first shot is viewed from the back yard.

This is the view from the front yard/courtyard.
This is the view from the front yard/courtyard.
The West side looking to the rear of the house.
The West side looking to the front of the house.
Monday, September 15, 2008
Basement Framing is Underway
These photos were taken a few days ago and show the framing has started in the basement. This first photo is looking towards 23rd Street from what will be the bedroom of the basement suite. The living room is to the right of this.

This photo is the living room mentioned above. Again, this is loking South towards 23rd.
Looking South from adjacent the trailer.
This photo is the living room mentioned above. Again, this is loking South towards 23rd.
This is looking South along the West foundation.
Overall view looking South towards 23rd Street.
Looking North from what will eventually be the front yard.
Thursday, August 28, 2008
Foundations
Concrete was poured on Monday, August 18 and the forms stripped a couple of days later. There was a bit of a bulge that the contractor came and ground out. Time that could have been spent applying the waterproofing. The weather was great for it. The company putting in the waterproofing and drainage mat was supposed to do the work yesterday, but things were wet in the morning when they arrived. Shame they didn't stick around, as the day turned out great. Nothing but rain is forecast now, so things are at a bit of a standstill.





Thursday, August 14, 2008
Formwork
For the past week, a crew of men have been putting together the formwork for the basement footings and foundations. Inspections should happen tomorrow once they finish up securing some of the horizontal rebar. Concrete is scheduled to be poured on Monday.
These shots are viewed from the back (North) of the property. The opening at the end will contain the French doors which will open onto the garden court.


The following shots are from the front (South) end of the property. The recess in the end is for the window wells to bring light into the basement of the North unit.
These shots are viewed from the back (North) of the property. The opening at the end will contain the French doors which will open onto the garden court.
The following shots are from the front (South) end of the property. The recess in the end is for the window wells to bring light into the basement of the North unit.